How Long Does It Take to Get a Business Sign?
Every step of a sign project in Colorado Springs, from the first site visit to the final inspection, how long each one takes, and what to put up on your storefront while you wait.

How long does it take to get a business sign? In Colorado Springs, vinyl and non-illuminated signs typically take one to two weeks and illuminated signs four to eight weeks, with permit review usually the longest step. A project moves through a site survey and estimate, design and proofing after the estimate is approved and the deposit is received, landlord approval, a sign plan approved by city Planning and a permit from the Pikes Peak Regional Building Department, production, installation, and inspection. Production can often run while the permit is in review. Window graphics within 25 percent of the window generally need no permit and can show your name in the meantime.
Most new businesses plan the opening date first and the sign second. The permit calendar does not care.
A business sign is one of the last things most owners think about and one of the first things customers see. The trouble is that a permanent exterior sign involves design, landlord approval, a city permit, production, electrical work, and installation, and several of those steps involve people outside your control.
This guide lays out each step of a typical Colorado Springs sign project, how long it takes, what slows it down, and how to get your name up while the permanent sign is in progress. For typical costs, see our guide to storefront signage costs for a new business.
The timeline at a glance
| Step | Typical time | Who is involved |
|---|---|---|
| Site survey and estimate | A few days | Sign company |
| Design and proofing | A few days to a week | Sign company and you |
| Landlord approval | Varies by landlord | Landlord or property manager |
| Permit | Varies, usually the longest step | City Planning and PPRBD |
| Production | Days for vinyl and panels, weeks for lit signs | Sign company |
| Installation and inspection | Usually a day, plus inspection scheduling | Sign company, electrician, PPRBD |
Overall, vinyl and non-illuminated signs typically take one to two weeks and illuminated signs four to eight weeks. Interior signs that do not need a permit are usually the fastest.
Step 1: site survey and estimate
A sign company measures the wall or frontage, photographs the building, checks the zoning and how much sign area the code allows, notes power for illuminated signs, and checks access for a lift. It also asks for the landlord's sign criteria.
This step matters more than it looks. A sign sized without checking the code or the landlord's criteria may have to be redesigned after it is rejected, which is one of the costliest kinds of delay. Our guide to wall sign permits explains how allowed area is calculated.
Step 2: design and proofing
Once the estimate is approved and the deposit is received, our team will begin the design and proofing process. The sign is placed at scale on a photo of your building so you can approve size, colors, materials, and placement.
This step moves fastest with a vector logo file and one person approving proofs. Each round of revisions typically adds a day or two.
Step 3: landlord approval
In shopping centers, office parks, and multi-tenant buildings, the landlord usually approves the sign before it goes to the city. Landlord sign criteria can cover letter style, color, size, illumination, and mounting, and some properties also operate under a coordinated sign plan approved by the city.
Response time depends on the landlord or property manager. Getting the criteria early and designing to them avoids a rejected proof.
Step 4: the permit
Colorado Springs adopted a new sign code in early 2026, Sign Ordinance No. 26-01, which took effect July 1, 2026. For most new permanent exterior signs, a sign plan is approved by city Planning before the Pikes Peak Regional Building Department (PPRBD) issues the permit. The plan shows the site, existing and proposed signs, wall signs on the building elevation, zoning, and the applicant and installer, and it needs written consent from the property owner.
Neither agency publishes a fixed review time. It varies with workload and how complete the application is. That makes the permit the least predictable step and usually the longest. Two things commonly hold it up:
- Incomplete applications, such as a missing elevation or unsigned owner consent.
- Existing illegal signs on the site. The city does not approve sign plans while illegal signs remain, including old banners or a previous tenant's unpermitted signs.
Our sign permit services page explains how we prepare and submit permits.
Step 5: production
Production time depends on the sign type:
- Vinyl and window graphics: days.
- Aluminum panels and dimensional letters: days to about a week.
- Channel letters and other illuminated signs: several weeks, because letters are fabricated, wired, and tested.
Production can often start while the permit is in review, once the design matches the submitted drawings, so the sign is ready when approval comes through. Our page on channel letter signs covers lit sign construction.
Step 6: installation and inspection
Most signs install in a day. Illuminated signs also need power to the sign location and a final connection by a licensed electrical contractor, then inspection. Some sign projects require engineered drawings based on the sign type, size, mounting method, and site conditions. We confirm the applicable requirements as part of the project review.
We handle the installation, including equipment coordination when needed, through the final walkthrough.
What to put up while you wait
If the opening date comes before the permanent sign, a few options can show your name in the meantime:
- Window graphics covering up to 25 percent of a ground-floor window generally need no permit and install quickly. See our window graphics page.
- Banners need a permit under the current code and are limited by size and by total days per calendar year.
- A-frame signs within the code's size and placement limits can be used during business hours without a permit, though placement in the public right-of-way needs a separate permit.
Feather flags are prohibited under the current Colorado Springs sign code.
How to shorten the timeline
- Start early. Begin the sign project when the lease is signed, not when the build-out is finishing.
- Get the landlord's criteria and the property owner's contact for consent right away.
- Send a vector logo and name one person to approve proofs.
- Clear old signs from the property, or ask the landlord to, before the permit is submitted.
- Plan power for illuminated signs during the build-out, when the electrician is already on site.
The Short Version
- Vinyl and non-illuminated signs typically take one to two weeks, and illuminated signs four to eight weeks.
- The permit is usually the longest and least predictable step.
- Under Colorado Springs' sign code, Planning approves the sign plan and PPRBD issues the permit.
- Incomplete applications and existing illegal signs on the site are common causes of permit delay.
- Production can often run while the permit is in review, so the sign is ready when approval comes through.
- Window graphics within 25 percent of the window can show your name while you wait.
Where this information comes from
- City of Colorado Springs, sign applications: coloradosprings.gov/signapp.
- Colorado Springs Unified Development Code, Part 13 Signs: codelibrary.amlegal.com.
- Pikes Peak Regional Building Department: pprbd.org.
- APG sign project records, Colorado Springs office.
Common questions
Sign Project Timeline FAQ
How long does it take to get a business sign in Colorado Springs?
In Colorado Springs, vinyl and non-illuminated signs typically take one to two weeks, and illuminated signs take four to eight weeks. Permit review is usually the longest step.
How long does a sign permit take in Colorado Springs?
The city and the Pikes Peak Regional Building Department do not publish a fixed review time. It varies with workload and how complete the application is, and it is usually the longest step in a sign project.
Can sign production start before the permit is approved?
Often, yes. Production can run while the permit is in review so the sign is ready when approval comes through, as long as the design matches the submitted drawings.
Why was my sign permit delayed?
Common causes of sign permit delays in Colorado Springs include a missing elevation drawing, unsigned owner consent, a design that exceeds allowed area or landlord criteria, and illegal signs remaining on the site.
What can I put up before my permanent sign is ready?
Window graphics covering up to 25 percent of a ground-floor window generally need no permit. Banners need a permit and have time limits, and A-frames are allowed within size and placement rules during business hours.
Are feather flags allowed while I wait for a sign?
No. The current Colorado Springs sign code prohibits feather, wave, blade, and sword banners, including as temporary signs.
How long does sign installation take?
Most signs install in a day. Illuminated signs also need a final electrical connection by a licensed electrical contractor and an inspection.
When should a new business start its sign project?
A new business should start its sign project as soon as the lease is signed. That leaves time for landlord approval and the permit, which are the least predictable steps.

APG: Advanced Printing and Graphics provides vehicle wraps, commercial signage, printing, apparel, promotional products, branding, and graphic design. APG is backed by industry experience dating to 2002 and has completed more than 3,000 projects and 1,000 installations. Our experience includes work for Colorado businesses and national brands such as Nike, Wells Fargo, Redken, and Warner Bros. APG was named a 2026 Best of the Springs winner in the design category by The Gazette and is a 2026 Best in Business finalist for outdoor marketing solutions with the Southern Colorado Business Journal.
Opening soon?
Tell us the date. We will plan backward.
Send the address, a photo of the building front, and your opening date. Our team will check the code and landlord criteria and send an estimate with a realistic schedule. Once the estimate is approved and the deposit is received, our team will begin the design and proofing process.